Monday 29 Apr 2024
By
main news image

KUALA LUMPUR (April 20): Petroliam Nasional Bhd (Petronas) is ready to start production from its Garagol Deniz West field in the Turkmenistan area of the Caspian Sea, Energy Voice reported.

Energy Voice is a digital and print news platform which reports on what matters in oil, gas, power and energy. 

This is some eight years after a platform jacket was installed, according to the portal.

The portal wrote that the jacket for an unmanned drilling and production platform was installed in 2015, but the topsides were only put in place earlier this month.

“Output from the field in Block 1 is expected to peak at 10,000 barrels per day of oil and 35 million cubic feet per day of gas,” Energy Voice reported.

As of writing, Petronas has yet to respond to queries from theedgemarkets.com concerning the report.

Edited BySurin Murugiah
      Print
      Text Size
      Share